 |
| |
|
    
|
|
Construction
Stake Out
| Construction
surveying is the translation
of construction plans into
physical points on the ground that
can be used as a basis for the
actual construction. The results
of construction surveying are seen
in almost any urban, suburban, and
even rural setting. Almost any
roadway, building, or other
man-made improvement probably had
some amount of construction
surveying involved. Construction
surveying provides not only the
horizontal location of new
improvements, but also the
vertical information required to
ensure that surfaces drain or
pipes flow as required. |
| |
The
stakes and points set during
the process of construction
surveying are not usually set at
the actual construction point, but
usually on some sort of offset.
This is done so that the survey
stake is not disturbed by
excavation or other activities
that will take place at the actual
point of construction. The stakes
are marked with an
"offset" and a
"grade", which provides
the construction crew with the
spacial relationship of the
construction stake to the actual
point of construction. The
"offset" is the distance
from the survey stake to the
horizontal position of the actual
point of construction, and would
typically be three feet for curb
and gutter to ten feet for
underground pipes. The distance of
the offset should be coordinated
with the contractor to accommodate
any specific needs due to existing
field conditions or special
equipment, and should be clearly
marked on the survey stake
(usually by a number enclosed in a
circle). The "grade"
represents the change in elevation
that needs to be obtained from the
reference point to the actual
construction point, expressed as a
"cut" (lower in
elevation) or a "fill"
(higher in elevation). The grade
should also indicate the vertical
feature that the grade is
referencing, usually a flowline or
finished floor elevation.
The need for accuracy is
inherent in all of the surveyor's
tasks, but especially evident in
construction surveying. It is not
only important to perform all
calculations correctly, but also
to communicate clearly with the
contractor about the distance of
offsets and reference points for
grades. If the surveyor provides
grades to the flowline of curb and
gutter and the contractor uses
those grades as top of curb
elevation, the net result is a
construction site that is not
going to work as planned!
Additionally, scheduling should be
coordinated in a manner that
minimizes the risk of the stakes
being damaged by human or natural
activities, as any disturbance to
the survey stake may carry over to
actual construction.
Just as division is the
inverse operation of
multiplication, construction
surveying is the inverse operation
of the activities with which the
surveyor is usually associated:
the gathering of data regarding
real points and positions on the
ground and representing those
positions on a map. The surveyor
performing construction surveying
is taking a "map"
representing proposed improvements
or structures and placing that
information on the ground. As you
can see, the surveyor is literally
involved from start to finish of a
construction project.
At NavTech we recognize the
need for survey measurements made
prior to or while construction is
in progress to control elevation,
horizontal position, dimensions
and configuration, and, following
construction, to obtain essential
dimensions for computing
construction pay quantities and
establishing "as built"
conditions. Construction Surveying
requires the expert skill of a
licensed practitioner well versed
in maintaining accuracy,
precision, efficiency, measuring
and computing values pertaining to
such surveys. A construction
survey may follow or be made in
lieu of a locative survey.
On average NavTech will perform
over 200 projects a year. These
construction sites can vary from a
new convenience store to a 1,000
megawatt power plant. |
|
|
|
|
|
|
|
|